Concrete Plant Expansion Permit - Windsor's Marentette Avenue
Official title: 2629045 Ontario Limited - Environmental Compliance Approval (air)
A ready-mix concrete plant in Windsor wants to double down on production. They're asking to increase capacity, add dust collectors, and upgrade their heating equipment. The catch? The plant emits nitrogen oxides, cement dust, and crystalline silica into the air.
Why This Matters
Live near Marentette Avenue in Windsor? This plant already releases dust and pollutants into your neighbourhood. More production could mean more emissions. If you have concerns about air quality, now's the time to speak up.
What Could Change
If approved, the plant could increase its concrete production capacity. New dust collectors would be installed, and the heating system would be upgraded. The permit would set limits on emissions of nitrogen oxides, particulate matter, and silica dust.
Key Issues
- Should the plant be allowed to increase its production capacity?
- Are the proposed dust collectors adequate to protect air quality?
- What are the health risks from increased silica and particulate emissions?
How to Participate
- Review the proposal details on this consultation page. Note that some supporting materials may only be available in person.
- Submit your comments by email to enviropermissions@ontario.ca or call 1-800-461-6290 for more information.