Should Hydro One Be Allowed to Expropriate Land for Transmission Lines in Port Colborne?

Official title: Continued operation of existing transmission facilities in Port Colborne

open Regulations & Permits Justice & Rights Natural Resources
Hydro One wants to expropriate private land in Port Colborne to keep operating existing transmission facilities. The affected landowner, Nyon Oil Inc., is fighting back. This Ontario Energy Board case will decide whether the utility can take the land and on what terms.

Why This Matters

Own property near power lines? This case shows how utilities can seek to expropriate land for infrastructure. The outcome could affect how similar disputes are handled across Ontario. A constitutional question has been raised, adding broader legal significance.

What Could Change

The OEB could grant Hydro One the right to expropriate the Nyon Oil property for continued transmission operations. Alternatively, it could deny the application or impose conditions. The constitutional question raised could set precedent for future expropriation cases.

Key Issues

  • Should Hydro One be granted expropriation rights over the Nyon Oil property?
  • What are the constitutional implications of the expropriation application?
  • What compensation or conditions should apply if expropriation is approved?

How to Participate

  1. Review the application documents to understand Hydro One's expropriation request.
  2. Review the public notice for information on how to participate in this proceeding.